GAO Report Slams Navy’s New Ford-Class Aircraft Carriers

The USS Gerald R. Ford is under construction at Huntington Ingalls Newport News Shipbuilding in Virginia.

U.S. Navy

AA Font size + Print

The USS Gerald R. Ford is under construction at Huntington Ingalls Newport News Shipbuilding in Virginia.

After delays and cost overruns, the USS Gerald Ford is now estimated to run $12.8 billion -- 22 percent more than planned, according to the Government Accountability Office. By Stephanie Gaskell

The USS Gerald R. Ford, the Navy’s newest aircraft carrier, won’t be ready for its planned 2016 commissioning due to poor testing, construction delays and cost overruns, a Government Accountability Office review warned Friday.

The ship’s “technical, design, and construction challenges” of the CVN78, the first of three new nuclear-powered aircraft carriers, “have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time,” the GAO said. “The Navy has achieved mixed progress to date developing CVN 78’s critical technologies, such as a system intended to more effectively launch aircraft from the ship.”

Meeting the 2016 deadline for commissioning the ship also will prove difficult, the GAO said. “Progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008 — to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.”

Delays and cost overruns for the USS Gerald R. Ford also threaten construction of the USS John F. Kennedy, the second of the Ford-class ships. GAO scoffed at the Pentagon’s cost estimate for the CVN 79 as “optimistic.”

The Ford-class ships are designed to give the Navy the ability to fly more aircraft on more missions than earlier carriers, boost margins for weight and stability so the ship’s contents can be reconfigured over its lifetime and has nearly three times the electrical generating capability. The Pentagon is spending $43 billion to build three of them.

In its response, the Navy said some of the findings of the GAO report were “overstated” but agreed to rework its testing schedule for the CVN 78, which is set for delivery in 2016, but won’t be deployable until 2019.

Read the full GAO report here.

Close [ x ] More from DefenseOne
 
 

Thank you for subscribing to newsletters from DefenseOne.com.
We think these reports might interest you:

  • Ongoing Efforts in Veterans Health Care Modernization

    This report discusses the current state of veterans health care

    Download
  • Modernizing IT for Mission Success

    Surveying Federal and Defense Leaders on Priorities and Challenges at the Tactical Edge

    Download
  • Top 5 Findings: Security of Internet of Things To Be Mission-Critical

    As federal agencies increasingly leverage these capabilities, government security stakeholders now must manage and secure a growing number of devices, including those being used remotely at the “edge” of networks in a variety of locations. With such security concerns in mind, Government Business Council undertook an indepth research study of federal government leaders in January 2017. Here are five of the key takeaways below which, taken together, paint a portrait of a government that is increasingly cognizant and concerned for the future security of IoT.

    Download
  • Coordinating Incident Response on Posts, Camps and Stations

    Effective incident response on posts, camps, and stations is an increasingly complex challenge. An effective response calls for seamless conversations between multiple stakeholders on the base and beyond its borders with civilian law enforcement and emergency services personnel. This whitepaper discusses what a modern dispatch solution looks like -- one that brings together diverse channels and media, simplifies the dispatch environment and addresses technical integration challenges to ensure next generation safety and response on Department of Defense posts, camps and stations.

    Download
  • Forecasting Cloud's Future

    Conversations with Federal, State, and Local Technology Leaders on Cloud-Driven Digital Transformation

    Download

When you download a report, your information may be shared with the underwriters of that document.